Project Tesla, Kettering Gateway

Project Overview

A project for SEGRO plc / Ball Engineering

Full turnkey construction of a new 660,000 sq ft building to operate as a can making facility.

Project Value:

£52.5 million

Project Duration:

49 weeks

Key Facts:

  • The building is split into four distinct areas which are the offices, the production hall, the storage area and the technical rooms
  • Detailed / complex M&E installations throughout the manufacturing hall
  • EPC A rated
  • The technical rooms act to support the 24 hour can production operation and house equipment, spares and supplies
  • Within the building there are a number of ATEX rated rooms that hold flammable liquids and specialist trenches and sumps to collect and hold liquid spillages