Works started with the demolition of the existing high bay warehouse and extensive ground works. The construction programme was sequenced to manage an extended period required to remove the ground floor slab of the previous warehouse that stood on the site. Complex negotiations were required to facilitate the removal of phone masts from the existing buildings.
£8.7 million
45 weeks (including demolition)